How Long Does It Take to Paint a House in Chelsea?

Published 15 June 2025


Understanding how long a painting project will take helps you plan around the disruption. Here are realistic timelines based on our experience in Chelsea properties — which, due to their period features and typically higher standards, often take longer than average London properties.

Room-by-Room Timelines

RoomDuration (1 painter)
Single bedroom1.5-2 days
Double bedroom2-3 days
Reception room2-3 days
Kitchen (walls & ceiling)1.5-2 days
Bathroom1-1.5 days
Hallway & stairs2-4 days
Landing1-1.5 days

**Note:** These assume standard Chelsea ceiling heights (2.7-3m). Higher ceilings add time. Rooms with extensive woodwork or period features add 50-100% to these timelines.

Whole-House Timelines

PropertyInterior OnlyInterior + Exterior
1-bed flat3-5 daysN/A
2-bed flat5-8 daysN/A
3-bed terrace8-12 days15-20 days
4-bed townhouse10-15 days20-30 days
Large family house15-25 days30-45 days

What Affects Duration

  • **Preparation needs:** Stripping wallpaper, making good damaged surfaces, and dealing with previous poor workmanship all add time
  • **Ceiling height:** Rooms above 3m require scaffolding setup time
  • **Number of coats:** Some colours require 3+ coats for even coverage
  • **Drying time:** Between coats (typically 4-6 hours for emulsion, overnight for woodwork paints)
  • **Period features:** Hand-finishing cornicing, mouldings, and panelling is painstaking work
  • **Weather (exterior):** Rain, frost, or very hot conditions can pause exterior work

How We Manage Timelines

We provide a detailed schedule before starting, typically working room-by-room through the property. We keep you informed of progress and any changes. Our goal is always to finish on time without compromising quality.